It was a moment of great pride for Kapil Mohan & Associates Pvt. Ltd., Chandigarh.., when their first hydro power project of 4 MW capacity was commissioned within 18 months from the date of ground breaking despite 3 months of work stoppage and bad weather conditions during commissioning in December 2010 and January 2011.
PDL was able to commission the plan within 14 months from the date of receipt of the advance despite external delays. This is quite an achievement for both JIRAH SHEP and PDL for having commissioned a power plant in 18 months when there are other taking close to 3-4 years to commission plants of such similar capacities.
JIRAH SHEP MILESTONE
Note: Erection contractor employed was HITECH Engineering Co., whose Managing Director is Mr. Vishwanathan. PDL is thankful to M/s HITECH for their excellent work and support during erection and commissioning of the power plant.
Note: For the first time PDL used Indigenous make AVR and Indigenous make Governor, which is operating very well with the KEM make Turbine and AC Generator.